LIFT
Aerial view of the completed Damasta HVDC converter station in its excavated mountain platform, north Crete
Infrastructure · Ariadne Interconnection · with TERNA

Damasta Converter Station

Crete’s end of the 1,000 MW power bridge to the mainland — the site drawn the way it was planned, then delivered.

1,000 MWTransfer capacity
±500 kVDC voltage
~330 kmCable to Attica
Top 3Deepest submarine links worldwide

Figures: Siemens Energy & IPTO (ADMIE) — the Crete–Attica interconnection

Project
Crete–Attica electrical interconnection
Owner
Ariadne Interconnection (IPTO)
Consortium
Siemens Energy · TERNA
Lydakis role
Building works on the converter halls, for TERNA
Location
Damasta, north Crete
Years
Details on request

The building that ended an island's isolation

For as long as anyone on Crete can remember, the island made its own electricity — expensively, in oil-fired plants. The Crete–Attica interconnection changed that: a 1,000 MW direct-current link running roughly 330 kilometres from the mainland grid, through some of the deepest water ever crossed by a power cable, to a terraced platform carved into a mountain saddle above the village of Damasta.

Lydakis delivered the building works on the converter-station halls — the structural shell that houses the direct-current interconnection between Crete and Attica — for TERNA, the consortium's civil-works contractor.

The station converts the direct current arriving from Attica back into alternating current for the Cretan grid — Voltage Source Converter technology behind the twin green-roofed halls in the photographs. According to IPTO, the link saves Greek consumers on the order of €500 million a year and cuts CO₂ emissions by about 1.5 million tonnes annually.

Ηλεκτρική διασύνδεση Κρήτης – Αττικής · Σταθμός Δαμάστας

The owner

Ariadne Interconnection · IPTO

Greece's transmission operator created a dedicated company to build the country's largest electricity interconnection.

The consortium

Siemens Energy & TERNA

Siemens Energy leads the converter-station consortium; TERNA carries the civil works and equipment installation.

On the ground

Lydakis Construction

When a project of national scale lands in Crete, the island's own builders deliver it — construction works at the Damasta site, for TERNA.

About the Crete–Attica interconnection

What does the Damasta converter station do?

It is the Crete terminal of the Crete–Attica electrical interconnection. The station converts the ±500 kV direct current arriving through roughly 330 km of cable from the mainland into alternating current for the Cretan grid — and back — using Voltage Source Converter (VSC) technology, with a transfer capacity of 1,000 MW.

Who built the Damasta station?

The interconnection is owned by Ariadne Interconnection, a subsidiary of IPTO (ADMIE), Greece's transmission operator. The converter stations were delivered by a consortium led by Siemens Energy with TERNA S.A. responsible for the civil works — and Lydakis Construction carried out construction works on the Damasta site for TERNA.

Why does the interconnection matter for Crete?

It ends the island's decades-long energy isolation. According to IPTO, the link saves consumers on the order of €500 million a year and reduces CO₂ emissions by about 1.5 million tonnes annually, replacing local oil-fired generation with power from the mainland grid.

Sources: Siemens Energy — HVDC power bridge press release · IPTO (ADMIE) — Crete–Attica interconnection

The twin converter halls and transformer bays of the Damasta HVDC station from the air
The converter halls · Damasta, Crete

Inside the Damasta converter station

Drag sideways — the professional shoot of the delivered station

Aerial view of the Damasta converter station in its excavated mountain bowl
Transformer bays and cooling banks beside the converter halls
Lattice transmission pylons beside the station buildings
The control building of the Damasta converter station
Converter hall elevation with transmission towers behind
Aerial overview of the excavated station platform
Electrical equipment room inside the station
Warehouse interior with equipment crates during fit-out
National-scale projectsTrusted on Greece's largest electricity interconnection — alongside Siemens Energy and TERNA.
Public-works contractorRegistered Greek public-works contractor delivering municipal and institutional projects across Crete.
Since 1978Three generations of engineering and construction on the island.
Start your project

Let's build it: from the first drawing to the keys

+30 2810 225586
Thank you — your request is in the Lydakis inbox. We will call you back within one working day.
In a hurry? Call +30 2810 225586 or write to info@lydakis.com.
Your email app just opened with the details filled in — press send and we will call you back within one working day.
Nothing opened? Email us at info@lydakis.com or call +30 2810 225586.
Looking to buy instead of build?Explore Lydakis Estate →